Special Report: The USA's Transformational Communications Satellite System(Global Information Grid)

Defense Industry Daily
Posted
: 2007-09-19 00:46:13

As video communications is integrated into robots, soldiers, and UAVs, and network-centric warfare becomes the organizing principle of American warfighting, front-line demands for bandwidth are rising sharply. The Transformation Communications Satellite (TSAT) System is part of a larger effort by the US military to address this need.

The final price tag on the entire TSAT program is expected to reach $14-18 billion through 2016, which includes the satellites, the ground operations system, the satellite operations center and the cost of operations and maintenance. By mid-2007, the U.S. Air Force will either decide to build the TSAT system on its current schedule and launch in 2013-2016, or postpone TSAT, take stopgap measures and add Advanced Extremely High Frequency (AEHF) satellites 4 & 5 to the three slated for launch from 2009-2012.

Lockheed Martin and Boeing have won a total of $514 million each in risk reduction contracts for the TSAT SS satellite system, in hopes of making that Plan B unnecessary. The bids are in, and both teams await a decision. TSAT's $2 billion TMOS ground-based network operations contract is already underway.

The TSAT constellation of satellites, receivers, and infrastructure has seen a recent resurgence of news coverage, and its central role in next-generation US military infrastructure makes it worthy of in-depth treatment. Yet its survival is not assured by any means. Outside events and incremental competitors could spell its end just as they spelled the end of Motorola's infamous Iridium service. This updated DID Special Report looks at the TSAT program, its challenges, and the potential future(s) of U.S. military communications. The latest developments include submitted bids from both TSAT-SS teams, and a contract to noted consulting firm Booz-Allen Hamilton…

Why TSAT Is Thought to be Necessary

ELEC_V-RAMBO.jpg
Israel's V-RAMBO

During 1991's Desert Storm operations, the U.S. military discovered that not only were they lacking in communications capacity, what they did have didn't connect very well. After September 11, experts learned that tremendous amounts of available information within and beyond the Defense Department required adequate connections among its various providers and users. Operations in Afghanistan, Iraq, and other battlefields of the Global War on Terror have further demonstrated the U.S. military's increasing reliance on high-tech communications and real-time data from UAVs, naval assets, and soldiers on the ground.

If bandwidth is becoming an important bottleneck in battle, went the question, what is the U.S. military to do?

Very shortly after the 9/11 attacks, the U.S. Department of Defense (DoD) initiated a Transformational Communications Study to accelerate the delivery of advanced capabilities with state-of-the art technology to the field. The study was led by the National Security Space Architect (NSSA), and used the NSSA's Mission Information Management Communications Architecture as a springboard. It looked at many options, and assessed current plans.

The study concluded that the US. Military's existing program plan would not meet forecast communications requirements. It also suggested that there was a window of opportunity to provide an architectural framework for a compatible communications system across the Department of Defense and the intelligence community – one that could increase U.S. capabilities by a factor of ten.

Those conclusions, plus ongoing experience in the Global War on Terror and new technology developments like UAVs, helped shape the Transformational Communications Architecture (TCA). At present, all of the U.S. services are making future acquisition plans that are dependent on the capabilities the TCA umbrella program is expected to provide.

The TSAT program is envisaged as part of the TCA, providing its space-based "anytime, anywhere" bandwidth backbone.

The Big Picture: TSAT and the Transformational Communications Architecture

ELEC_TCA_Collage.jpg

The TSAT Program is actually just one node in a broad spectrum of programs known as the Transformational Communications Architecture (TCA), version 1.0 of which was approved by a Joint Requirements Oversight Council Memorandum (JROCM) on October 23, 2003.

TSAT's status as one of a constellation of communications initiatives offers opportunities for synergy, but it also creates complications. The U.S. military, intelligence community, and NASA satellite constellations operate independently, and each of the three communities is responsible for securing the funding for its own satellites. While their programs are designed to be compatible with each other, priorities between these groups sometimes differ. In addition, the separation of funding and lobbying means that technical elements designed to work together may not be funded synchronously. For instance, while the Defense Department manages the TSAT, the U.S. intelligence community is working on the optical relay communications architecture, and NASA manages the tracking and data relay satellite system (TDRSS-C).

This is part of the task facing the newly-formed Transformational Communications Office.

Communications satellites come in three flavors: narrowband systems like IRIDIUM that suffice for voice transmissions but lack bandwidth, wideband systems for sending large amounts of data, and protected satellites that are 'protected' against jamming and nuclear effects. TCA v1.0 makes use of all three.

The TCA envisions a Global Information Grid (GIG) that includes the Wideband Global SATCOM (WGS) for unprotected wideband, the Mobile User Objective System (MUOS or next generation narrowband) scheduled for launch in 2009, the Advanced Extremely High Frequency (AEHF next generation protected, a.k.a. Milstar III) to be launched between 2008-2011, an Advanced Polar System for various strategic missions, and the Transformational Communications Satellite (TSAT) system that could be launched from 2013 as a major upgrade, instead of deploying AEHF #4 & 5.

These programs are all organized around the lifespan of the current Milstar II satellite constellation; the Pentagon is highly confident that they will remain capable through 2014, but after that confidence diminishes.

What Is TSAT?

SPAC_Satellite_TSAT.jpg
TSAT SS Concept

TSAT is intended to provide internet-like capability that extends high-bandwidth satellite capabilities to deployed troops worldwide, and delivers an order of magnitude increase in available military bandwidth. Using laser communications intersatellite links to create a high data-rate backbone in space, TSAT will be one of the key enablers for the American vision of Network Centric Warfare.

A visual image from a UAV that would take 2 minutes to process with the Milstar II satellite system would take less than a second with TSAT. A radar image from a Global Hawk UAV (12 minutes), or a multi-gigabyte radar image from space-based radar (88 minutes), would also take less than a second with the TSAT network. Best of all, the recipient can be on the move with a relatively small receiver, anywhere in the world.

As Military Information Technology explains, TSAT users fall into two broad categories: high-data rate access users and low-data rate access users. The high-data rate access provides a data rate of 2.5 gigabits to 10 gigabits per second through laser communications. However, only 20 to 50 or so of these links would be available, and they will most likely be dedicated to major intelligence, surveillance and reconnaissance assets in space and in the air.

Others on the low data-rate end can still use about 8,000 simultaneous radio frequency (RF) data links, which will provide connectivity to strategic assets and tactical users as well as the aerial intelligence, surveillance and reconnaissance (ISR) platforms. The high data rate platforms have drawn the most attention, but the ability to covert high data throughput into thousands of RF channels is likely to prove equally important.

The whole TSAT system will include TSAT Space Segment (TSAT SS) satellites, as well as integrated ground stations and networks. For instance, the $2 billion TSAT Mission Operations System, (TMOS) is part of the TSAT program, and also has wider applications.

As noted earlier, Lockheed Martin and Boeing have won $514 million each in risk reduction contracts for the TSAT SS satellite system.

As of June 14/07, the Boeing team included Ball Aerospace, BBN Technologies, Cisco Systems, EMS Technologies, General Dynamics, Harris Corp., Hughes Network Systems, IBM, L-3 Communications, LGS Innovations, Raytheon, and SAIC.

The Lockheed Martin TSAT SS team includes Northrop-Grumman, Juniper Networks, ViaSat, Rockwell Collins, General Dynamics Advanced Information Systems, L-3 Communications, Stratogis and Caspian Networks.

TMOS: TSAT's Ground Component

ELEC_Network_Operations_Center.jpg
NOC example

The TMOS network will give the U.S. military's overall Transformational Communications Architecture (TCA) the ability to act as a broadband, on-demand global Internet based on IP, incorporating key emerging network technologies like quality of service provisioning and bandwidth guarantees in the bargain. TMOS is expected to provide operational and network management for the TSAT Space and Ground communications segments, connecting the USA's future TSAT SS ultra-high-bandwidth satellite backbone into the US military's evolving Global Information Grid.

Troy Meinke, the Air Force TSAT program manager, explained it this way to Military Information Technology:

"Basically, TSAT is the overall system. The satellites are part of that, the ground segment is part of that, and TMOS is part of the overall TSAT system."

The critical part of TMOS will be writing nearly 5 million lines of software code, which accounts for about 80% of program development. To try and avoid software development problems that have plagued other large space programs, the US Air Force has enlisted experts from the Software Engineering Institute. The TMOS program also includes the development of a network operations center (NOC) and operations management center, as well as the related hardware.

Overall, the TMOS network will give the U.S. military's overall Transformational Communications Architecture (TCA) the ability to act as a broadband, on-demand global Internet based on IP, incorporating key emerging network technologies like quality of service provisioning and bandwidth guarantees in the bargain. TMOS will provide circuit/packet mission planning and policy management, external network coordination, network operations and management, key management, and Situational Awareness-Common Operational Picture in a secure environment, fully incorporating cyber-security.

As Trip Carter, advanced programs manager for military satellite communications at Raytheon, put it to C4ISR Journal:

"In the future it could be cost prohibitive to do so once networks are out there and established and deployed. Lots of transformation systems emerging today and the time to achieve interoperability is now."

The Pentagon says that awarding TMOS early decreases TSAT program risk by providing an integrating construct for network architecture and design, and allows the awarded contractor to begin work on formal network interface definitions and specifications. Earlier in the competition, Raytheon spokespeople had also noted that TMOS stations could be built before the satellites are launched in 2013, and used in conjunction with existing resources as part of the Global Information Grid Bandwidth Extension project.

The majority of TMOS' ground-based functionality is scheduled to be up and running approximately a year prior to launch, so that MILSATCOM can test the TMOS network and prepare it to work with the TSAT SS satellites. The hope is that the winning contractor can begin incremental deployment of the network around 2008, then build up to support the planned 2012-2013 launch using a spiral development process, adding incremental features and tests at each "mini-release" point.

Contracts for the TMOS segment of the system involved $3 million for preliminary research to each of 3 consortia led by Lockheed Martin, Raytheon, and Northrop-Grumman. Lockheed's consortium then went on to win the $2.02 billion TMOS contract in January 2006, and the firm announced a successful Systems Design Review milestone in June 2006.

AEHF and Lessons Learned for TSAT

SPAC_AEHF_Satellite.jpg
AEHF Milstar III
(click to view full)

While they may be inferior to the TSAT SS, Advanced Extremely High Frequency (AEHF) Milstar III satellites will provide over ten times the capacity and six times higher data rate transfer than that of the current Milstar II satellites.

The AEHF's phased array antenna is being developed by Northrop-Grumman, and will direct radio frequency beams electronically rather than moving reflectors mechanically. The uplink phased array antenna will connect the AEHF spacecraft with ground terminals, while minimizing jamming effects and the possibility of signal intercept by enemies. The steered agile beams will allow AEHF satellites to connect more areas simultaneously with highly protected channels, and it will do so faster than Milstar.

As a result of multiple factors, however, including the U.S. NSA's failure to provide cryptographic solutions in time, AEHF is currently facing a 12 month schedule slippage, and a significant cost increase over previous projections. In April 2005, DID covered some of the issues associated with current U.S. satellite programs generally, and has also done a comprehensive round-up of AEHF Milstar III contracts that shows the key issues and their effects on program costs and schedule.

This slippage has forced Congressional notification, and it is also forcing a number of changes. Some of them are seeping into the TSAT program as well, as it incorporates AEHF lessons-learned into its acquisition strategy.

For instance, as a result of its AEHF Milstar III failures, National Security Space Acquisition Policy 03-01 was revised to include information assurance readiness from agencies like the National Security Administration (NSA) as a critical factor at key decision points in space systems development. NSA, with community-wide support, is also attempting to establish a new space cryptographic research and development program to develop core information-assurance technologies that will be available for integration by new space programs, thus reducing concurrent development risk. More details regarding the AEHF program, measures taken, and TSAT can be found in this C4SIR Journal article: "First Launch of Advanced Communications Satellites Slips."

Other TSAT project approaches also derive from past experience. The decision to procure the ground-based TMOS separately from the TSAT SS satellites, for instance, is designed avoid some of the problems experienced with systems such as Wideband Gapfiller and the AEHF satellites which have their own specialized and incompatible ground systems. Another advantage is that the US military won't be forced to compromise between the development of the network and the development of the satellites as it selects vendors. With TMOS, the satellite component will be a router within the network, working with other systems and tying in with the whole concept of the TCA's Global Information Grid.

Which brings us to the associated question "which satellites will they be?" as we look at the TSAT program's looming issues and decisions.

TSAT: Program Issues & Decisions

GOV_GAO_Logo.jpg

Soon, the US military will make a major decision: whether to limit the acquisition of the Advanced Extremely High Frequency (AEHF) communications satellites in favor of developing a newer generation of laser-linked satellites, known as the Transformational Satellite Space Segment (TSAT SS).

The AEHF program is running over cost and schedule, but it incorporates more mature technologies. TSAT promises dramatically greater bandwidth and processing capabilities and is considered integral to DOD's efforts to network all of its weapon systems, but there is much less certainty as to how much the system will cost or when it can be delivered because critical technologies are less mature. Ultimately, the question facing the Transformational Communications Office is whether the TSAT program can successfully integrate leading-edge technologies in time to provide its advertised capabilities, or whether AEHF satellites with just 1/20 the bandwidth capacity represent a safer bet that is guaranteed to deliver something to a bandwidth-starved military.

The reality of space programs is harsh, and unbending. They cannot use the standard 'fly, fix, fly…' development approach because the vehicle is placed in orbit. Which means the Air Force has just one shot to be successful. This changes one's risk calculus, and one's systems engineering overhead and methodologies as well.

A General Accounting Office (GAO) report published in December 2004 faced this issue squarely. It recommended that TSAT be delayed until its critical technologies, such as laser optics, high-speed router and security algorithms, are more mature. Most of these technologies were rated at technology readiness level (TRL) 3 or 4 by the GAO, which translates as technologies in the study stage with some laboratory tests. The GAO also pointed to a lack of backup technologies for critical systems such as laser communications.

In response, the TSAT program took steps to address some of those gaps. One step was moving the launch date back from 2009 to 2012, in order to give technologies more time to develop. For instance, Lockheed Martin said recent developments in laser communications and space-qualified Internet protocol routers mean TSAT has a better chance at success. Another step was to award risk reduction contracts to study alternatives, refine the expected development path, and beef up preliminary research in key areas. These alternative possibilities include options that may sacrifice certain features for more proven alternatives. Efforts in this vein continue, and TSAT's planned deployment date is now closer to 2014.

A September 2005 GAO advisory noted improvements on the technology front, but integration remained a concern. As one Senate source told Aviation Week, integration of the technologies "can be a technology in and of itself, and hard to do, and that's where a lot of our space programs have failed."

Nor is that the only reason they have failed.

GEO_Capitol_Building.jpg

US House Armed Services Strategic Forces Subcommittee Chairman Terry Everett [R-AL] openly wonders: "Can the current acquisition system accommodate the risks associated with the current business model and actually produce what it promises?" When the deployment horizon is a decade out and end of service life is 35-50 years in the future, changing requirements can be hard on a program. Especially in a field exploding as fast as electronics and networking. That horizon itself can lead to serious problems with requirements creep – as ranking member Silvestre Reyes [D-TX] has noted: "We get started using a Volkswagen frame and then all the add-ons … just completely overwhelm what we started with." Pedro Rustan, director of advanced systems and technology in the National Reconnaissance Office, concurs and adds that rigid requirements and budgetary compartmentalization plus a lack of program contingency funds are a recipe for trouble.

What we're seeing here is an age-old conflict between new technologies, which always involve a certain amount of risk, vs. an approach that sticks with mature technologies. Procurement approaches in need of reform exacerbate both the need to take the risks associated with the new new thing, and the level of the risk that results when one does so. It is not a pretty picture, and it can be found throughout the US military space programs. Barring sudden reform, however, decisions must be made within the environment one has, not the environment one wishes we had.

The bottom line remains. Mature technologies are less risky over the short term, but they limit innovation and may lack enough "upside" to meet longer-term needs. As an earlier DID article noted, if the goal of the current set of satellite systems is bleeding edge dominance for reasons of planning or policy, then given the requirements of space launches, the GAO's findings throughout the TSAT program are what one would expect as the price for having that capability potential.

Will the US continue to make that choice, and pay that price? The next couple of years will be a key go/no-go decision time for the TSAT's position within the overall Transformational Communications Architecture.

A decision to build AEHF #4 & 5 would indicate a feeling that TSAT was not going to be ready in time. That decision would then force a cascade of other decisions:

  • Should the Department of Defense ask for an overall budget increase to pay for the additional AEHF satellites?
  • Should it reduce other programs elsewhere to pay for them?
  • Or should the DoD take the money out of the TSAT program in the short term, and stretch the TSAT program's timeline by funding it over a longer period?

Removing funds from TSAT delays the program further, and may increase its overall costs. That could require even more AEHF launches over that lengthened time frame in order to keep pace with front-line needs. The rising costs of TSAT can even become a self-fulfilling prophecy, tipping the cost/benefit balance even further toward deploying last-generation solutions. Something like this dynamic can already be seen in the F-22 Raptor fighter jet program, for instance. In addition, when we're talking about IT investments, each older satellite launched entrenches older architectures and so reduces future flexibility.

These dilemmas may be common to most cutting-edge military projects, but that does not make them any less formidable. Fortunately, as we've seen in the AEHF lessons learned section, the integrated nature of the Transformation Communication Architecture's programs can be a help as well as a hindrance.

Conclusion: TSAT's Competitors – and Its Fate

ELEC_Laptop_Soldier.jpg
Got bandwidth?

There is little question that high-bandwidth capabilities will be needed on the front lines, and soon. Network-centric warfare is here. Will the network it requires be there for America's military over the next 5 years? How about the next 25 years, which is the required planning horizon?

Making that happen won't be easy. Some failures and setbacks are inevitable. Yet there is little question that TCA is coming. One key issue is how well the Transformational Communications Office can leverage the failures into valuable lessons that help other TCA projects and programs succeed. If they're up to these challenges, the TCA still won't be a complete success and probably won't be on budget, either – but it will be good enough, overall, to meet many of its promises and make a big difference on future battlefields.

In the life and death arena of military purchases and global geopolitics, that would make the TCA's costs money well spent.

Which leads to our final question: will TSAT SS be part of that network?

One of the assumptions that's worth thinking about is whether the budget for TSAT will continue to be there. Consider current US budgetary realities, the ongoing and unpredictable cost of a global war, the coming "maintenance overhang" for worn out equipment, outside events, and finally a wide array of under-funded Pentagon programs that reaches far beyond just the space field. Under those circumstances, a $15-18 billion satellite network that could cost $20 billion or more in the end and won't be ready for another 10 years is a prime target for program cuts.

In terms of long term trends, it's also worthy of note that a combination of narrowband satellites and MARTS-type communications aerostats for theater communications, wideband AEHF satellites for mission-critical high-bandwidth transfers like UAV video, encrypted communications via commercial satellite carriers, and laid fiber-optic cables for strategic communications are already appearing on the scene.

Every one of these components is already deploying, and both the US military and global economic forces will continue to add to their availability incrementally. As such, one can also expect every one of these infrastructure pieces to become more prevalent in the coming years. Throw in the possibility of finding new ways to leverage existing systems, and this constellation definitely represents a potential "incremental competition" threat to TSAT.

Which is why another key issue for TSAT and TCA is how well the Transformational Communications Office and its programs are documenting their assumptions about the future, checking them periodically to ensure that those assumptions are still valid, and building upgradeability and flexibility into their platforms and plans so they can cope with changes to those assumptions. In other words, they'll need to be good at all the things Motorola didn't do with its disastrous IRIDIUM global cellular network, which ironically now carries narrowband traffic for the U.S. military at bargain prices.

Could TSAT share IRIDIUM's fate at an even earlier stage, shot down by a creeping incremental set of competitors even before it launches? It could. Could TSAT continue to improve, and turn out to be an expensive but important program success story? It could. Some of the choice between those fates lies in the hands of its contractors and managers. some of it lies in the upper reaches of the Pentagon. Some of its fate, however, lies entirely outside all of their hands.

In the end, one does not fight the war one wishes – one fights the war one must, the way one must. The USA is at war, which means that TSAT – like so many other US weapons programs – is now afloat on the tides of war, politics, chance, and change. Will it go under in the end, or come to safe harbor? We shall see.

(Here at DID, we will continue to watch this program and update this profile. Reader tips, insights, and corrections are always appreciated. Email joe, here at defenseindustrydaily dot com).

TSAT: Timeline and Recent Developments

SPAC_Satellite_Ground_Systems_Generic.jpg
Tracking…

Sept 14/07: Booz Allen Hamilton, Inc. in McLean, Virginiareceived a contract modification for $6.6 million, to provide additional Systems engineering and Integration (SE&I) effort and other direct costs in support of TSAT program segments during FY 2007 and FY 2008 At this time $1,156,000 has been obligated.

Sept 13/07: Jane's International Defense Review offers some perspective on bandwidth issues:

"To understand the pressure navies worldwide are under to increase bandwidth capacity, consider the following US Navy (USN) predicament: In 2006, USN total bandwidth capacity per second was 197.2 million Mega bits per second (Mbit/s). The US Naval Studies Board reports that the USN's Littoral Combat Ship (LCS) alone will demand 8 Mbit/s during normal operations and 20 Mbit/s when deployed."

July 30/07: Teams led by Boeing and by Lockheed Martin/ Northrop Grumman submit their bids for the TSAT space segment. Aviation Week | Boeing release.

July 23/07: The Lockheed Martin/Northrop Grumman TSAT team announces the formal addition of Juniper Networks, Inc. to its partnership team. Juniper Networks has been supporting Northrop Grumman for the past 3 years in developing the Next Generation Processor/Router (NGPR) for the TSAT system, which will use Internet Protocol routing on board the satellites to connect users with the Global Information Grid.

Juniper's JUNOS is the routing control software being fielded across Juniper's widely used commercial routers and was the first IPv6 software approved for use by the Defense Department, which has fielded JUNOS software and Juniper's router hardware for terrestrial use in the GIG network. Juniper has licensed its JUNOS software product for Northrop Grumman's use. NGC release.

June 6/07: Boeing announces the results of its NGPR-2 tests at MIT's Lincoln Laboratory. NGPR-1 confirmed compatibility with the gold-standard TSAT terminal using the XDR+ waveform. NGPR-2 used the government's assigned TSAT Radio Frequency Universal System Test Terminal (TRUST-T) and Network Standards Test and Verification Environment (NSTVE), measured data transmission and lag time from a user perspective, demonstrated dynamic bandwidth resource allocation, and provided compatibility and network demonstrations. Finally, Boeing's TSAT team displayed several key enabling technologies as a head-start to planned future demonstrations in multi-terminal environments.

Boeing's TSAT team has successfully completed all 37 government- defined demonstrations on time, as they compete with Lockheed Martin's team for the upcoming TSAT Space Segment award.

June 5/07: Lockheed Martin announces a successful System Design Review (SDR) of the TSAT Mission Operations System (TMOS) with the U.S. Air Force. The 2-day event concluded the system review of TMOS architecture and requirements allocation for this critical element of the Global Information Grid. Lockheed Martin release.

The Space Segment Request for Proposal (RFP) is scheduled for release in the near future, and a decision on the winning contractor team for the Space Segment is expected later in 2007.

March 20/07: Boeing announces a new set of U.S. Air Force test results from MIT's Lincoln Laboratory in Lexington, MA, which used TSAT to deliver high-power operations at 3 data rates (2.5, 10, and 40 gigabits/second). They were designed to validate the system's performance to, and interoperability with, government laser communications standards. The tests also verified the traceability of results achieved during a February 2006 demonstration, and evaluated the capabilities and performance of the upgraded telescope, new optical high-powered amplifier, and additional data rate during pointing, acquisition and tracking tests.

The brassboard-level hardware suite demonstrated consists of a precision space telescope and pointing electronics developed by Ball Aerospace & Technologies Corp.; an optical high-powered amplifier developed by LGS Innovations (formerly Lucent Technologies) and a low noise amplifier and optical modems developed by Boeing.

Additional Boeing-funded demonstrations and environmental testing of the components in early 2007 will support the government's requirement for laser communications maturity prior to the Space Segment Design Review in April 2007.

Jan 26/07: FCW quotes Air Force Lt. Gen. Charles Croom, director of the Defense Information Systems Agency, who says that continuing schedule slippage in TSAT development of the Transformational Satellite System (TSAT) means that DOD users will not be able to use 5 planned satellite constellations with a total of 28 gigabits/sec throughput, until 2016. The original plan called for them to be ready by 2009. The article also mentions relays via high-altitude balloons and UAVs like Global Hawk as temporary substitutes, and puts the replacement commercial market bandwidth bill at about $1 billion:

"Croom said the satellite development delays resulted from "trying to cram too much capability intestate," making a reference to jam-resistant laser cross-links between satellites. Croom urged an accelerated launch of three satellite Wideband Gapfiller satellite systems to help meet DOD's satellite broadband needs.

Dec 4/06: Boeing announces a successful demonstration of communication capabilities between its TSAT laser communications terminal and BAE Systems' Airborne Lasercom Risk Reduction Terminal (ALT), which included a telescope, optical bench assembly, and closed-loop pointing and tracking hardware. The demonstration was prepared, executed and funded by Boeing, BAE Systems and Ball Aerospace Technologies Corp., in parallel with the government's effort on each program.

The demonstration used several optical waveforms to route TSAT communication signals through the ALT Risk Reduction Terminal at data rates of up to 10 gigabits per second. On command, the TSAT terminal dropped its link to the ALT risk reduction terminal and acquired and established communications with a second emulated TSAT terminal. Testers then reversed the process to illustrate the system's agility.

At this point, the Boeing team includes Raytheon, Ball Aerospace, General Dynamics, IBM, L-3 Communications, Cisco Systems, BBN Technologies, Hughes Network Systems, Lucent Technologies, Harris, EMS Technologies, ICE and Alpha Informatics.

Oct 28/06: The US Navy is experimenting with aerostats for communications relay, surveillance, and radar overwatch functions – and this has become a formal program, as NAVSEA and NAVAIR sign a memorandum of understanding to develop a sea-based 38-meter aerostat prototype with a weather hardened design that can carry up to 500 pounds of surveillance equipment. They will use a 32 meter aerostat they've been experimenting with as a base platform, and want to develop it to accommodate a modular, interchangeable payload system that can offer radar, optronics, communications, or set combinations for maximum flexibility. That's NAVSEA's area of expertise. The ultimate goal of the program is to develop a sea-based 71-meter, weather-hardened aerostat sensor platform, with larger interchangeable payload modules, capable of operating at an altitude of up to 15,000 feet. See full DID coverage: "Return of the Navy Blimps?"

Aug 9/06: Boeing announces completion of the TSAT Space Segment's quarterly program management review, overseen by the U.S. Air Force Military Satellite Communications (MILSATCOM) Joint Program Office and representatives of the TSAT user community, including the U.S. Strategic Command, Air Force Space Command, Secretary of the Air Force, Army Forces Strategic Command, Office of the Assistant Secretary of Defense and the Space and Naval Warfare System Command. Using the Transformational Communications Demonstration Capability (TCDC) live, virtual, and constructive simulation and test environment to emulate the military's JTRS Radio System, Boeing engineers showed how the two systems would operate together. The tests included simulations of real-world conditions such as blockages due to rough terrain, loss of terminals in the network and fully loaded capacity utilization.

The review also provided progress updates in other key areas, including specification maturation, the TSAT block development approach, software architecture development, and the path to full-scale Space Segment and software integration.

Aug 1/06: Boeing announces a successful demonstration at MIT Lincoln Laboratories, where they linked from one satellite to another using a laser beam in a simulated space environment. The demonstration, marked the 3rd of 4 planned laser communication milestone demonstrations.

MIT/LL rated the free-space optical link operation at speeds of up to 40 gigabits per second, which enables the broadcast of 3,000 simultaneous high-definition TV channels, or about 15,000 regular TV channels, in each direction. They also tested the Boeing hardware for performance and compatibility with the U.S. government's new Lasercom Interoperability Standard, as well as the performance readiness of Boeing's TSAT optical modems.

Equally critical to the success of Lasercom on TSAT is the Pointing, Acquisition and Tracking (PAT) subsystem, which enables the effective use of Lasercom's beam, providing significant advantages in transmitted power requirements. The PAT subsystem uses Ball Aerospace Technology Corp.'s proven, robust algorithms and beam control technology. The demonstration verified Ball's design approach and technology to be consistent with the Lasercom Interoperability Standard, which fulfills another risk reduction objective for TSAT.

June 20/06: Boeing announces success in a series of live tests demonstrating the interoperability of the Transformational Satellite Communications (TSAT) Next-Generation Processor Router (NGPR) with a government reference ground terminal, held at MIT's Lincoln Laboratory (MIT/LL). The test used the government's TSAT Radio Frequency Universal System Test Terminal, and verified Boeing's initial compliance and compatibility with the XDR+ anti-jamming waveform, developed for TSAT ground-to-satellite connections.

May 24/06: The US Government Accountability Office releases report #GAO-06-537: "Space Acquisitions: DOD Needs Additional Knowledge as it Embarks on a New Approach for Transformational Satellite Communications System."

"The Department of Defense is not meeting original cost, schedule, and performance goals established for the TSAT program…. TSAT's current formal cost estimate is nearly $16 billion and the initial launch date has slipped to September 201… the initial delivery of capability will be less than what DOD originally planned. ....While senior DOD officials have agreed to these reduced capabilities to get the first satellite launched in 2014, DOD has yet to reevaluate its investment in TSAT in light of other DOD investments using the knowledge it has now gained. Using this new knowledge, DOD could be in a better position to set more realistic goals, before entering product development."

March 31/06: The U.S. Air Force identified laser communications as a key risk technology needed for TSAT. Team Lockheed and Northrop-Grumman announce the successful completion of a preliminary compatibility test of the high-data-rate laser communications hardware to meet a newly-defined U.S. government lasercom interoperability standard. The testing demonstrated a single-access optical aperture, which is the front end of a communications terminal that uses a laser to transmit and receive information. See this DID article for more details.

Jan 27/06: Lockheed Martin's team wins the TMOS contract for TSAT's ground-based network management system. See DID's coverage.

December 2005: The FY 2006 defense budget Congress sends to U.S. President George W. Bush in December 2005 gives the Pentagon only about half of the $836 million it wanted for TSAT, directs the U.S. Air Force to focus on maturing the needed technology for the program, and makes $120 million of the $436 million provided contingent on analyzing whether more satellites like the Wideband Gapfiller or the AEHF will be needed prior to the first TSAT launch. If so, that $120 million could go to fund them instead. "Transition to a formal acquisition program should be deferred until the technologies are mature and have been demonstrated in a relevant environment," the conferees wrote. See full C4ISR Journal Article.

Oct 24/05: GAO's opinion of TSAT technology readiness improves, but integration is still a concern. Their formal report due in early 2006, but Aviation Week has coverage of the interim document.

June 23/05: The US Government Accountability Office releases General Accounting Office report #GAO-05-570R – Defense Acquisitions: Incentives and Pressures That Drive Problems Affecting Satellite and Related Acquisitions. Among other notes, it says that the amount of bleeding-edge technology in the TSAT program is a major risk factor.

Sept 28/05: The Boeing-Raytheon team completes two more TSAT SS satellite program milestones. The Space Segment Requirements Review requires a demonstration of requirements comprehension, allocations and design implementation status. In addition, a Risk Reduction Requirements Review milestone was also completed involving a proposed baseline architecture. Read Boeing's corporate release for more details.

July 12/05: Boeing announces that the Transformational SATCOM Space Segment (TSAT SS) satellite program successfully completed its Interim Space Segment Design Review (ISSDR). Boeing's team bridges networking and telecommunications with military satellite experience. Other members include Raytheon, Ball Aerospace, General Dynamics, Cisco Systems, IBM, L-3 Communications, BBN Technologies, Hughes Network Systems, Lucent Technologies, Harris, EMS Technologies, and Alpha Informatics. Boeing's corporate release has more details.

July 6/05: A Lockheed Martin /Northrop Grumman TSAT SS satellite team completes an Interim Space Segment Design Review (ISSDR). During the review, the team reviewed in detail its planned architecture and design approach for the system, and summarized results of risk reduction efforts. A highlight of the review was an extensive exhibit hall that featured brass board-level hardware, demonstrations of key technologies, and displays summarizing performance, mission scenarios, and user benefits. The TSAT end-to-end network test bed was configured with three TSAT payloads, interconnected with a high-speed Synchronous Optical Network (SONET) backbone, two Special Operations satellite terminals and a Brigade Combat Team satellite terminal. This consortium also includes ViaSat, Rockwell Collins, General Dynamics Advanced Information Systems, L-3 Communications, Stratogis and Caspian Networks. Read Lockheed's corporate release for more.

April 4/05: Lockheed Martin Space Systems in Sunnyvale, CA received a $41.7 million cost-plus fixed-fee contract modification for an eight-month stretch out to the TSAT definition/ risk reduction phase, due to funding reduction in FY 2005 & 2006. FY 2005 funding had been reduced by $90 million, from $202 million to $112 million (-45%), while FY 2006 funding was increased by $50 million (+25%) from $200 million to $250 million. A replan of the contract was conducted which accommodates the funding reduction, and also incorporates development of information assurance products for transmission security and telemetry tracking and command crypto. Work will be complete by December 2006. The Headquarters Space and Missile Systems Center at Los Angeles Air Force Base, CA issued the change (FA8808-04-C-0023, P00009).

Feb 14/05: The Air Force Research Laboratory at Kirtland Air Force Base, NM, awards two contracts to create a brass board terminal assembly to Technology Readiness Level 5 (component-level validation in a relevant environment) no later than October 2006. It is part of the MALST (Multi-Access Laser Space Terminal) program, and the technology will be transitioned to TSAT. Work will be complete by April 2007. Winners include Boeing Satellite Systems in El Segundo, CA ($14.8 million, FA9453-05-C-0166), and Northrop Grumman Space and Missile Systems Corp. in Redondo, CA ($14.8 million, FA9453-05-C-0167).

Feb 1/05: Boeing Satellite Systems in El Segundo, CA received a $41.9 million contract modification for an eight-month stretch out to the TSAT definition/ risk reduction phase, due to funding reduction in FY 2005 & 2006. FY 2005 funding had been reduced by $90 million from $202 million to $112 million (-45%), while FY 2006 funding was increased by $50 million (+25%) from $200 million to $250 million. A replan of the contract was conducted which accommodates the funding reduction, and also incorporates development of information assurance products for transmission security and telemetry tracking and command crypto. The Space and Missile Systems Center in Los Angeles Air Force Base, CA issued the change (FA8808-04-C-0022, P00008).

Dec 27/04: Stung by difficulties with a number of its satellite programs, the US Air Force makes some changes to The National Security Space Acquisition Policy 03-01, which set out procurement policies in this area. DID has coverage and links.

Jan 22/04: The Headquarters Space and Missile Systems Center at Los Angeles Air Force Base, CA issues a pair of cost-plus fixed-fee contracts for the transformational communications military satellite communication space segment (TSAT SS) risk reduction and system definition phase. The scope of activities for this effort include a robust risk reduction program (e.g. laser communication subsystem, satellite processor/router subsystem) and the necessary program management and systems engineering to develop an initial design of a system of survivable Satellite Operations Center, and continental US gateway elements that are capable of the TCM requirements. Lockheed Martin in Sunnyvale, CA (FA8808-04-C-0022) and Boeing Satellite Systems in El Segundo, CA (FA8808-04-C-0023) receive roughly $472 million each. Work will be complete by March 2006.

Additional Readings & Sources: TSAT Background & Analysis

  • Lexington Institute (Aug 15/07) – TSAT: Essential to Security [PDF format, 2.6 MB]. The Lexington Institute has been a strong backer of the program for some time now. This is their full-length briefing on the subject.
  • Space Review (Sept 6/05) – TSAT: unobtainium urgently needed. "If the space systems procurement people want to rebuild some confidence in the project, they might want to consider rethinking what they mean when they say 'risk reduction.' "

Official Reports

Additional Readings & Sources: Related Programs

  • TelecomWeb ViaSatellite.com articles. See esp. "The Military Sector: Doing Business With The Decisionmaker" [Part I | Part II]. Part I describes current US satellite programs and trends within the TCA's framework, while Part II focuses more on the doing business aspect.
  • The Space Review (June 19/06) – Will China Compel the Development of GPS 4? "This will mean that the current GPS 3 program will have to be curtailed or modified beyond recognition. The generation after next of GPS satellites will have to include much more robust methods for overcoming or avoiding enemy interference…. In the long term this could create some interesting opportunities for the Transformational Satellite (T-Sat) communications program to work with the designers of the future GPS system."
  • DID (Jan 16/06) – Lockheed Gets $491.2M for AEHF Satellite 3 and Launch Support. DID explains the AEHF program in depth, and adds a history of over $4 billion worth of AEHF-related contracts that clearly describe some of the issues the program has faced, their financial impacts, and some of the new system's capabilities.
  • DID (Nov 22/05) – 3 Wideband Gapfiller Satellites to Get Pedigree Reviews. The Pedigree Review rigorously audits all critical components and subsystems, and is designed to help ensure that the satellite will work fully in the "one chance to get it right" environment that characterizes space-based equipment. DID also adds links to analysis and data re: the WGS program itself.
  • DID (Nov 4/05) – Pentagon's Global Broadcast System Matures. What do you do when bandwidth is tight, and you want to take the load off of your satellites but still get large files out into the field? Enter GBS, whose future is linked to the Wideband Gapfiller….

Additional Readings & Sources: TSAT-Related News

  • DID (Jan 30/06) – Lockheed's Team Wins $2.02 Bn TSAT-TMOS Contract. This $2.02 billion cost-plus award fee contract is for the TSAT's ground-based Mission Operations System (TMOS). Raytheon and Northrop-Grumman has also received research funds
  • Military Information Technology (June 13/05) – Network of Nations. Describes the U.S. military's role as a satellite communications supplier to allies in Iraq.

Additional Readings & Sources: Related Analysis

  • Dartmouth college, Tuck School of Business – Learning from Corporate Mistakes: The Rise and Fall of Iridium (see also PDF version). A compelling cautionary tale from the corporate sector that illustrates the perils of not re-examinaing and challenging one's assumptions in the middle of the process. Motorola did not. Result: Iridium's market didn't need it any more, but Iridium didn't have the bandwidth to do much else. Motorola took a $1 billion loss, and Iridium became one of the 20 largest bankruptcies in US history.
  • Clay Shirky's "Permanet, Nearlynet, and Wireless Data" offers some useful insights as well, though it's important to remember that unlike corporate executives, militaries really do need connectivity anywhere as a life-and-death matter and this changes some of the dynamics involved.

 

We The People Radio Network

Who's online

There are currently 0 users and 3 guests online.

Listen To The IntelStrike Report

Vote For Us On Podcast Alley

The IntelStrike Report Radio Show Is Hosted By Doug Owen and Michael Vail.
Broadcast Live Monday - Friday 7:00 -9:00 PM CST

Listen To The Live Shows On The TruthNet Radio Online Streams Below

Winamp
16k
Windows Media
Real Audio

Check Out TruthNet Radio Online
Interact With The Show In The TNR Chat Room